The following pictures are the COT Electric crew rigging the poles before they are raised in building of the DOC Electric Transmission Line.  Click on the pictures to enlarge them.

Taken the week of February 25, 2008:

Taken the week of March 3, 2008:

Week of March 10, 2008:

Electric Substation at Prison Site:

Construction is set to begin during the latter part of the week of March 3rd with the pouring of the foundation for the substation.

Substation Site

Substation Transformer has arrived:

Taken the week of February 25, 2008:

Click on this link:

Pole Removal

Evergreen Construction was contracted to pour the concrete foundations for the steel poles installations on the DOC Transmission Line.  Click on the pictures to enlarge them.

Click on pictures to enlarge them.

Taken the week of March 3, 2008:

All of the foundations for the steel electric poles have been poured and are ready for pole installation.